Crestwood Modulating Furnace Upgrade: 2018 Single-Stage Replacement With 2-Year AC Retention Phased Approach
Case study summary: 1990 Crestwood ranch with end-of-life 30-year-old single-stage gas furnace (Bryant 313AAV from 1995); customer had recently replaced AC in 2023 (Carrier 24ABB6 2.5-ton, 2 years old) and wanted to retain new AC equipment while upgrading furnace; furnace-only replacement with new Carrier Performance 96 modulating furnace (60,000 BTU 96% AFUE); existing ductwork and AC retained; existing thermostat upgraded to Carrier Infinity touchscreen for variable-capacity furnace integration with existing two-stage AC; total project cost $7,800; completed in 1 day during November 2025. Outcome: 31-36% reduction in heating gas consumption; smoother furnace operation pairing well with existing two-stage AC; phased equipment replacement plan allowed customer to spread investment across multiple years.
The Home
- Built: 1990
- Style: Single-story ranch with attached two-car garage
- Location: Crestwood, MO 63126 (1980s-1990s subdivision)
- Size: 1,820 sf single level plus 1,400 sf finished basement (3,220 sf total conditioned with basement included)
- Construction: Wood frame with brick veneer; concrete block walls on basement; original windows replaced with vinyl in 2017; attic insulation upgraded to R-49 in 2018
- Existing heating: Bryant 313AAV (80,000 BTU/hr 80% AFUE single-stage gas furnace from 1995, 30 years old at time of replacement)
- Existing cooling: Carrier 24ABB6 2.5-ton two-stage AC from 2023 (2 years old, well within service life); previous AC was Bryant 463A 2.5-ton from 1995 (replaced 2023 due to R-22 compressor failure)
- Ductwork: Sheet metal supply trunks from 1990 with adequate sizing; some sealing improvement opportunity during installation
- Existing thermostat: Honeywell programmable thermostat installed during 2023 AC replacement; not communicating-equipment-compatible with new modulating furnace
The Situation
Customer contacted us in September 2025 about furnace-only replacement. Drivers:
- Furnace equipment status: 30 years old, well past typical 18-25 year service life; pressure switch replacement (2024) and inducer motor replacement (2025) signaled end-of-life pattern
- Recent AC investment: customer had spent $5,800 on AC replacement in 2023 due to R-22 compressor failure; this equipment was high-quality (Carrier 24ABB6 two-stage) with 8+ years remaining service life expected
- Phased equipment strategy: customer wanted to spread equipment replacement across multiple years rather than do simultaneous full-system replacement; furnace replacement now, AC replacement when needed in approximately 2031-2033
- Variable-capacity equipment opportunity: customer interested in modulating furnace benefits (longer cycles, better distribution, quieter operation) without doing full-system replacement
Initial assessment confirmed furnace-only replacement scope:
- Existing Carrier 24ABB6 AC compatible with new modulating furnace through Carrier Infinity touchscreen thermostat (communicating equipment protocol supports both)
- Existing ductwork and refrigerant connections retained without modifications
- Equipment location in utility room adequate for new equipment
- Thermostat upgrade required for variable-capacity equipment integration but otherwise minor scope
The Equipment Selection
Carrier Performance 96 Modulating Furnace (Selected)
- AFUE: 96%
- Capacity: 60,000 BTU/hr input (Manual J calculation showed 52,000 BTU/hr design heating load; previous 80,000 BTU was oversized for actual home load; 60,000 BTU provides appropriate margin)
- Technology: Modulating gas valve with variable-speed ECM blower; 40-100% modulation range
- Warranty: 10-year parts, 20-year heat exchanger
Carrier Infinity Touchscreen Thermostat
- Communicating equipment protocol compatible with both new Carrier Performance 96 furnace AND existing Carrier 24ABB6 AC
- Provides integrated variable-capacity control across heating and cooling modes
- Replaces previous Honeywell programmable thermostat (which couldn’t fully integrate with two-stage AC even before furnace upgrade)
Alternative Equipment Considered
- Carrier Performance 80 (80% AFUE non-modulating): lower cost ($1,800 less); selected against because efficiency gain wouldn’t justify investment and modulating operation provides comfort benefits
- Carrier Comfort 92 (92% AFUE two-stage non-modulating): middle option ($800 less than modulating); selected against because modulating equipment provides better long-term value
- Trane S9V2 modulating: equivalent equipment from different manufacturer; selected against because Carrier brand match with existing AC equipment provides integration benefits
- Heat pump alternative (Carrier Performance 38MURA): would have replaced gas heating; customer chose gas continuation based on operational familiarity and modest projected operational savings
The Project Scope
Pre-Installation
- Crestwood Public Works permit: Pulled within 4 business days (mechanical permit only for furnace replacement)
- Equipment ordering: 7 business days for Carrier Performance 96 furnace and Carrier Infinity touchscreen thermostat
- Installation scheduling: November 2025 before peak heating season
Installation Day 1 (November 14, 2025 – single-day installation)
- Morning (8:00 AM – 11:30 AM): Existing furnace isolation and shutdown; gas line capped; electrical disconnected; old furnace removal (300 lbs, removed via utility room to garage to outdoor disposal vehicle); chimney venting disconnected; existing AC connections protected during furnace work
- Mid-day (11:30 AM – 12:30 PM): Ductwork inspection and modest sealing improvements at supply and return trunk connections; old chimney venting verified disconnected from active heating equipment
- Afternoon (12:30 PM – 4:30 PM): Carrier Performance 96 furnace placement; gas line reconnection; electrical connection; PVC venting installation through utility room exterior wall (replacing previous chimney venting); condensate management routing to existing utility room floor drain; existing AC plenum and refrigerant connections verified intact
- Late afternoon (4:30 PM – 6:30 PM): Carrier Infinity touchscreen thermostat installation; furnace commissioning with Bacharach combustion analysis (CO 11 ppm air-free, CO2 9.6%, O2 5.5%); communicating equipment configuration; system performance verification in heating mode; AC integration verification (cooling mode test); customer walk-through
- End of Day 1: equipment fully installed and operational; chimney top sealed with stainless steel cap (chimney no longer used for venting; preserved as architectural feature)
Inspection (November 21, 2025)
- Crestwood Public Works inspector visit; installation passed inspection
The Pricing
- Carrier Performance 96 60,000 BTU modulating furnace: $3,400 equipment
- Carrier Infinity touchscreen thermostat: $580
- Installation labor (1 day, 2 technicians): $1,600
- Ductwork sealing scope: $280
- PVC venting installation through exterior wall: $480
- Crestwood Public Works permit: $200
- Old equipment removal and disposal (300 lb furnace): $240
- Bacharach combustion analysis and commissioning: $200
- Chimney cap installation (sealing unused chimney for moisture protection): $180
- Drywall and paint patches at thermostat location: $80
- Communicating equipment configuration and AC integration testing: $200
- Miscellaneous fittings, hardware, and consumables: $160
- Total project cost: $7,600 rounded to $7,800 with permit contingency and installation variances
This pricing fell within our standard range for furnace-only replacement with thermostat upgrade ($6,800–$9,400 for modulating furnace + communicating thermostat installations).
The Outcome
Heating Performance
- First-winter operation (November 2025 – March 2026): System maintained setpoint reliably with substantially quieter operation than previous single-stage equipment
- Modulation benefits: equipment running at 40-55% capacity during typical winter conditions provides longer cycles and more even distribution; customer notes basement temperatures more consistent with main level
- Quieter operation: customer reports dramatic noise reduction vs. previous 30-year-old equipment
Integration with Existing AC
- Two-stage cooling integration: existing Carrier 24ABB6 two-stage AC now integrated through Infinity touchscreen; previous Honeywell thermostat couldn’t fully utilize two-stage operation
- Improved cooling performance: even though AC equipment unchanged, control upgrade through Infinity thermostat enables previously-unused two-stage capabilities; verification during spring 2026 cooling-mode operation
- System longevity: 2-year-old AC equipment expected to provide 8-13 more years of service before replacement consideration; furnace-only replacement preserved this investment
Energy Performance
- First-winter gas consumption (Nov 2025 – Mar 2026): approximately 980 therms vs. previous winter (Nov 2024 – Mar 2025) consumption of 1,460 therms — 33% reduction
- Annual gas savings at $1.20/therm: approximately $575 reduction in annual heating costs
- Simple payback on installation: approximately 13-15 years on heating efficiency savings alone; faster considering equipment reliability and avoided emergency replacement risk
Customer Feedback
Customer reported high satisfaction with several aspects: furnace-only approach preserved 2-year-old AC investment; modulating operation noticeably quieter and more even than predecessor; smart thermostat provides remote monitoring and integration with existing AC capabilities; single-day installation minimal disruption; phased equipment plan allows future AC replacement at natural end-of-service-life without simultaneous full-system investment.
Ongoing Service
Customer enrolled in maintenance plan covering furnace and existing AC; both pieces of equipment serviced together annually under unified maintenance scope.
Frequently Asked Questions
- Why replace only the furnace if both pieces of equipment are over 25 years old?
- Customer’s situation involved recent AC replacement creating asymmetric equipment age that supported furnace-only replacement. Recent AC replacement history (this customer): 2023 AC replacement was forced by R-22 compressor failure on previous Bryant equipment; customer invested $5,800 in new Carrier 24ABB6 two-stage AC at that time; new AC equipment has expected 10-15 year service life remaining as of 2025. Decision analysis – replacing both vs. furnace only: replacing both equipment now would discard 2-year-old AC with 8-13 years remaining service life; that’s substantial wasted equipment value; furnace-only approach extracts full value from previous AC investment while addressing immediate need. When to replace both pieces of equipment simultaneously: equipment of similar age both at or approaching end of service life; matched-system benefits valuable for customer; budget supports full-system replacement; planning for long-term equipment longevity. When phased replacement makes sense: significant age difference between heating and cooling equipment (this customer’s situation); recent investment in one piece of equipment; budget constraints requiring spreading investment across years; customer comfortable managing equipment replacement timing actively. Compatibility consideration: new modulating furnace + existing two-stage AC integrates well through communicating thermostat; brand consistency (Carrier furnace + Carrier AC) supports integration; cross-brand integration possible but more complex; integration capability should be verified during quote development. For this customer’s situation: phased approach extracted full value from 2023 AC investment; matched-brand integration through Carrier Infinity thermostat provides system benefits without simultaneous full-system replacement; customer can plan AC replacement for 2031-2034 timeframe when natural end of service life approached. For other customers in similar situations: evaluate actual remaining equipment life; phased approach extracts more value from existing equipment when remaining life is substantial; full-system replacement appropriate when both pieces of equipment are at similar ages.
- How does the communicating thermostat improve operation of existing AC?
- Modern smart thermostat unlocks two-stage capabilities of existing AC that previous thermostat couldn’t access. Why previous Honeywell thermostat limited two-stage AC: Honeywell programmable thermostat from 2023 installation was basic equipment selected by previous contractor at time of AC replacement; thermostat provided basic two-stage AC control but without sophisticated coordination; equipment ran on simple capacity stage selection based on temperature difference; couldn’t optimize stage selection for variable-capacity equipment benefits. Carrier Infinity touchscreen thermostat improvements for existing AC: communicating equipment protocol allows direct AC interface (not just contact closure like basic thermostats); equipment runs at optimal capacity stage based on actual demand and operating conditions; smart staging logic provides longer cycles at low stage when appropriate; improved coordination with modulating furnace for transition between modes. Specific operational improvements: low-stage operation more frequent (~70% of cooling time at low stage vs. ~50% with previous thermostat); longer cycles improve humidity removal; more even distribution from longer cycle airflow; reduced cycling reduces equipment wear. Quantifying improvement: customer’s spring 2026 cooling-mode verification shows slightly lower energy consumption vs. previous summer despite no equipment change; estimated 6-10% improvement in cooling efficiency through better staging logic; minimal but measurable improvement. For other customers considering thermostat upgrades alone: communicating thermostats can improve two-stage and variable-capacity equipment performance even without other equipment changes; cost $400-$800 for thermostat upgrade vs. potential 5-15% efficiency improvement; worthwhile investment when paired with existing communicating-compatible equipment. Why thermostat upgrade matters specifically: many customers don’t realize that thermostat selection affects equipment performance beyond basic on/off control; sophisticated equipment requires sophisticated control to deliver full capabilities; thermostat is often overlooked component of equipment upgrade decisions.
- What’s the value of single-day installation vs. multi-day projects?
- Furnace-only replacement is dramatically simpler than full-system replacement, supporting same-day completion. Single-day installation feasibility for furnace replacement: gas line reconnection straightforward; electrical connection simple; venting installation moderate scope; thermostat upgrade quick; commissioning standard; total scope manageable for 2-technician team in single day. Compared to full-system replacement timing: typical 2-day project for matched furnace + AC replacement; refrigerant work adds time (recovery, vacuum, charge); two equipment installations require sequencing; additional commissioning scope. Customer benefit of single-day installation: minimal home disruption; no extended period without heating capability during winter season; customer can plan day for installation rather than multi-day inconvenience; less stress about equipment installation process. Single-day installation requirements: existing equipment in accessible location; no asbestos abatement coordination needed (this would require multi-day project); ductwork serviceable without major modifications; existing connections compatible with new equipment; clear weather for outdoor equipment work if applicable. When single-day installation isn’t feasible: complete heating system replacement (with new ductwork requirements); custom equipment configurations requiring fabrication; asbestos abatement coordination (multi-day project); unusual installation locations or access challenges. For this customer’s installation: standard utility room equipment location; existing ductwork retained without modifications; furnace-only scope; standard equipment configuration; single-day installation appropriate. Cost implications of installation duration: $1,600 labor for single-day installation vs. typical $2,400-$3,200 for 2-day installation; reduced labor cost reflects simpler scope rather than rushed work quality. For customers considering furnace-only replacement: single-day installation typical when scope is straightforward; reasonable customer expectation for furnace-only project; multi-day projects appropriate when scope warrants but shouldn’t be assumed required.
- When does it make sense to replace AC during furnace replacement vs. waiting?
- Customer-specific decision based on AC age, condition, and economic factors. Replace AC during furnace work when: AC is older than 12-15 years (within typical 15-20 year service life); AC has experienced significant repair history; AC uses R-22 refrigerant (becoming expensive and difficult to service); matched-system benefits substantial; customer prefers single project disruption; budget supports full-system replacement. Wait on AC when: AC is recent (under 5-7 years for typical equipment); AC has clean repair history; AC equipment is high-quality with substantial remaining life; budget supports phased approach better than full-system; customer comfortable managing equipment timing actively. For this customer’s situation: 2-year-old Carrier 24ABB6 AC with 8-13 years remaining service life; replacing now would waste substantial remaining equipment value; phased approach preserves AC investment; future AC replacement (2031-2034 estimated timeframe) can be matched with then-current technology. Cost-benefit analysis – replace now: $7,800 furnace only + future AC replacement in 6-9 years vs. $13,500 full-system replacement now; phased approach total cost approximately $14,000-$16,000 (current furnace cost + future AC); slightly higher total cost over period; benefits are preserved AC investment and ability to use latest technology for future AC. Customer decision approach: evaluate actual remaining equipment service life; consider operational benefits of full-system replacement (matched equipment, simultaneous upgrade); evaluate budget across phased vs. simultaneous replacement; consider customer’s planning preferences. For this customer’s situation: phased approach made sense given recent AC investment; we present both options during quote development and let customer make informed decision; many customers in similar situations choose phased approach; some prefer full-system for simplicity. For customers facing this decision: consider remaining equipment life as primary factor; brand integration possible across brands but Carrier-to-Carrier or Trane-to-Trane provides simplest integration; communicate timing preferences during quote development.
- What’s the long-term cost comparison: gas furnace vs. heat pump for this scenario?
- Heat pump alternative discussed but customer chose gas continuation for specific reasons. Heat pump alternative scope for this customer: would have replaced gas heating with Carrier Performance 38MURA heat pump (3-ton, 17 SEER2 cooling rating, electric backup heating); would have required replacing existing 2-year-old AC equipment (heat pump integrates with air handler, not gas furnace); cost approximately $13,200 for heat pump + air handler vs. $7,800 furnace-only approach. Heat pump pros for this customer: gas service eliminated (operating cost dependence on electricity only); environmental benefit of electrification; potentially lower long-term operating costs (if electricity prices remain stable relative to gas); preserves AC functionality through heat pump cooling capability (heat pump doubles as AC). Heat pump cons for this customer: would have required replacing 2-year-old AC equipment (substantial wasted investment); higher upfront cost ($13,200 vs. $7,800 = $5,400 premium); electricity cost during cold weather backup heating; uncertainty about long-term electricity cost trends; existing gas service infrastructure being abandoned. Customer decision factors: substantial AC investment already made (2-year-old equipment with significant remaining service life); existing gas service reliable and relatively economical at $1.20/therm; customer not actively pursuing electrification goals; phased equipment replacement strategy in place; cost-benefit ratio for heat pump conversion didn’t justify in current situation. Long-term cost projection: gas furnace approach over 20-year period – $7,800 furnace replacement + future AC replacement $9,000-$11,000 + 20 years of natural gas operating costs at $1,400-$1,800 annually = $44,800-$55,400 total cost over 20 years; heat pump approach over 20-year period – $13,200 heat pump installation + AC equipment service over 20 years + 20 years of electricity heating costs at $1,300-$1,700 annually = $39,200-$47,200 total cost over 20 years; heat pump shows modest long-term advantage but with significant uncertainty about energy price trends. For other customers considering this comparison: evaluate actual current equipment condition; consider long-term home plans (electrification preferences, anticipated home sale timing); consider energy price preferences (electric vs. gas); discuss with quote development to evaluate specific situation. For this customer’s situation: phased gas furnace approach was right decision given specific circumstances; heat pump remains future option when AC reaches natural end of service life in 2031-2034 timeframe. We present both options during quote development; customer makes informed decision based on their priorities.
Contact Purisync Heating and Air
For your furnace-only replacement, phased equipment replacement strategy, or thermostat upgrade with existing equipment integration in Crestwood, contact our 325 N Kirkwood Road office at (314) 338-5111. Initial consultation includes Manual J load calculation, evaluation of existing equipment compatibility, equipment options across multiple manufacturers, phased vs. full-system comparison, and written quote with itemized pricing.
- Emergency Line (24/7): (314) 338-5111
- Address: 325 N Kirkwood Rd #245, Kirkwood, MO 63122
- Email: info@purisyncheatingairconditioning.xyz
- St. Louis County Mechanical Contractor License: #MC-2014-08439-STL
- Kirkwood Business Registration: #BL-2014-1187
- EPA Section 608 Universal: #608U-2014-385721